December Construction Update

Progress continues to be made at North River Road as the City of West Lafayette installs infrastructure that will prevent stormwater and wastewater overflow from polluting the Wabash River.
Closure of North River Road and Happy Hollow Road intersection extended due to poor ground conditions and utility delays

The closure of North River Road and its intersection with Happy Hollow Road has been extended through Spring 2023 due to poor ground conditions and third-party utility delays.
November Construction Update

Construction continues under North River Road as the City of West Lafayette installs infrastructure that will prevent stormwater and wastewater overflow from polluting the Wabash River.
October Construction Update

Work continues under North River Road between Happy Hollow Road and Dehart Street as the City of West Lafayette installs a large tank that will hold up to 1.2 million gallons of stormwater and wastewater overflow, preventing it from polluting the Wabash River.
Construction underway 30 feet under River Road

Construction is underway on North River Road between Happy Hollow Road and Dehart Street. Thirty feet under the roadway, a large tank is being constructed to hold up to 1.2 million gallons of stormwater and wastewater overflow, preventing it from polluting the Wabash River.
River Road CSO project launches May 16, brings temporary closures and greener infrastructure

Starting on May 16, 2022, River Road and its neighboring Parks and Recreation trail will be closed at Happy Hollow Road south to Dehart Street. This closure is part of the City of West Lafayette’s ongoing effort to improve its stormwater and wastewater collection system and prevent future pollution of the Wabash River. This closure […]